By Lam Legal | Reviewed by Ada P. Lam
Short Answer
In British Columbia, a builders lien usually has to be filed within 45 days.
The tricky part is figuring out when that 45-day clock actually starts.
When a certificate of completion is issued, the deadline may run from its date. If there is a head contractor, it may instead run from when the head contract is completed, abandoned, or terminated. Without a head contractor, the deadline may run from completion or abandonment of the improvement.
These deadlines are strict. If you miss the one that applies to your project, you can lose your builders lien rights against the property.
So What’s the 45-Day Builders Lien Deadline in British Columbia?
Let’s say a subcontractor finishes a renovation job and leaves the site. A few weeks later, the invoice still hasn’t been paid. They assume the 45-day builders lien deadline started on their last day of work.
That may not be the case.
BC’s Builders Lien Act gives contractors, subcontractors, workers, and material suppliers certain lien rights when they provide work or materials to a construction project. But those rights come with strict deadlines.
The triggering event determines when the 45-day lien period begins. The Act identifies three main events:
- A certificate of completion is issued. The lien generally has to be filed within 45 days of the date on the certificate.
- There is a head contractor. If a certificate of completion does not apply, the deadline may run from when the head contract is completed, abandoned, or terminated.
- There is no head contractor. In that case, the deadline may run from when the improvement itself is completed or abandoned.
A certificate of completion also has to follow the process set out in the Act. The payment certifier must post it in a prominent place. Problems with how it was requested, issued, or posted can sometimes mean it did not actually start the 45-day period. A later certificate does not restart the deadline if an earlier certificate already started it.
Does the Deadline Start When You Finish Your Own Work or When the Head Contract Ends?
If the owner hired a head contractor to handle substantially all of the project, the deadline for lien claimants may be tied to the head contract, rather than to the day an individual subcontractor finished its part of the job.
For example, a plumber might finish work several weeks before the overall project is completed. That does not necessarily mean the plumber’s 45-day clock started when they left the site.
What If the Property Owner Is Acting as Their Own General Contractor?
A homeowner might hire the electrician, plumber, carpenter, and other trades directly instead of hiring one general contractor to manage the whole job.
In that situation, the 45-day deadline may run from when the improvement itself is completed or abandoned, rather than when one individual trade finishes its work.
What Counts as Completion?
“Completion” does not necessarily mean every item of work has been performed.
Under the Builders Lien Act, a project can be considered completed once it has been substantially completed or performed, including where it or a substantial part of it is ready for its intended use.
So a few unfinished details do not necessarily keep the lien clock from starting.
Coming back later to fix deficiencies or perform remedial work also does not necessarily give you a new 45-day period.
What Does Abandonment Mean?
Under the Act, a contract or improvement may be considered abandoned after work has stopped for 30 days.
There are exceptions. For example, the rule may not apply if the stoppage was caused by weather conditions, holidays, or another similar cause.
Simply planning to return to the project later does not necessarily mean the project has not been abandoned. What matters can include why the work stopped in the first place.
What Happens If You Miss the 45-Day Deadline?
If you do not file a builders lien within the deadline that applies to your project, the lien against the land is generally extinguished.
These time limits are strictly enforced by BC courts. They generally cannot simply give someone extra time because the deadline was missed.
A late lien may still initially be registered, but it can later be challenged and cancelled. A registered lien appears on the property title and can complicate a sale or financing. It does not always have to be paid before it can be removed from title. In some cases, the lien may be removed by paying money into court or providing sufficient security, while the claim continues against that money or security. Liens also have priority over judgments issued after the lien takes effect, which is generally when the relevant work began or the first materials were supplied.
Missing the deadline also does not necessarily mean the underlying debt disappears. A contractor or subcontractor may still have a contractual claim for the unpaid money through a lawsuit.
Filing a lien also carries risks if it is wrongful. A person who files against an interest in land to which the lien does not attach may be liable for costs and damages caused by the filing. Separately, a court may cancel a lien it finds frivolous, vexatious, or an abuse of process. An excessive claim amount alone should not be described as automatically creating liability.
Filing the lien is also not the final step. A separate one-year limitation period applies to starting an action to enforce the lien and registering a certificate of pending litigation. Miss that deadline and the land lien can also be lost.
Is There Still a Claim Against the Holdback If the Land Lien Is Lost?
BC law also recognizes a separate lien against statutory holdback money, sometimes called a Shimco lien.
This is different from the builders lien registered against the land. Losing the land lien does not automatically eliminate a possible claim against an existing holdback.
There must actually be an available holdback fund, and the claim has to be asserted before the money is paid out. See our article on statutory holdbacks for more information.
BC courts have held that this separate holdback lien is not subject to the same 45-day filing deadline as the land lien. The BC Court of Appeal reaffirmed this principle in Kingdom Langley Project Limited Partnership v. WQC Mechanical Ltd., 2025 BCCA 169.
However, this protection is set to change. BC’s new Construction Prompt Payment Act includes amendments to the Builders Lien Act that will abolish Shimco liens. The legislation has received Royal Assent but is not yet in force. Until the amendments take effect, Shimco liens remain available under existing law.
For more information, see our article on BC’s Construction Prompt Payment Act.
Do the Same Builders Lien Deadlines Apply to Homeowners?
Generally, yes.
There is no separate 45-day rule just because the project involves a house or is relatively small. What matters is how the project is structured.
If a homeowner hires one general contractor to handle substantially all of the work, there may be a head contract. If the homeowner hires the trades directly, there may not be.
In a small project under $100,000, a homeowner may not be required to create a separate holdback account. However, for the contractors, there is no difference and you can still file a lien for any claim above $200.
What About Builders Liens on Strata Lots?
Strata developments have another deadline to watch.
When an owner developer transfers a strata lot to a buyer, the lien generally has to be filed by whichever comes first:
- the deadline that would normally apply under the Builders Lien Act; or
- 45 days after the strata lot is transferred to the purchaser.
That means the sale of a strata unit can sometimes move the deadline forward.
Will BC’s New Prompt Payment Law Change the 45-Day Builders Lien Deadline?
No. BC’s new Construction Prompt Payment Act will not change the existing 45-day deadline for filing a builders lien against land. Although the legislation has passed, it is not yet in force.
The new law will make several changes to construction payments and holdbacks. In particular, it will reduce the statutory holdback period from 55 days to 46 days when the relevant provisions take effect.
Under the Builders Lien Act, the person primarily liable on a lienable contract or subcontract must retain a 10% holdback based on the greater of the value of the work or materials provided and the amount of any payment made on account of the contract price.
However, the holdback period and the deadline for filing a builders lien are two different things. The 45-day filing deadlines under section 20 of the Builders Lien Act will remain unchanged.
As discussed above, the new legislation will also abolish Shimco liens once the relevant amendments come into force.
Frequently Asked Questions
Legislation
Builders Lien Act, SBC 1997, c 45
Construction Prompt Payment Act, SBC 2025, c 24
Strata Property Act, SBC 1998, c 43
Questions about an unpaid construction account or a builders lien in British Columbia? Book a Free Discovery Call or call 604-800-0774 to discuss your situation with Lam Legal Trial Lawyers.
This article provides general legal information only and is not legal advice. Builders lien deadlines can depend on the structure and history of a particular construction project.